top of page

Generator Commissioning: Step-by-Step Procedure & Checklist

elearning@ensemble

Commissioning of Generator

Generator commissioning is a critical process that ensures the safe, efficient, and reliable operation of a diesel generator (DG) before it is put into service. A properly commissioned generator minimizes the risk of electrical faults, mechanical failures, and operational inefficiencies.

This blog outlines the step-by-step commissioning process, including pre-commissioning inspections, electrical and mechanical tests, safety checks, and load testing.

1. Pre-Commissioning Checks

Before starting the generator, the following pre-installation inspections must be conducted:

1.1 Physical Inspection

✔ Ensure the generator is installed on a level foundation.

✔ Check for any physical damage or loose connections.

✔ Verify the alignment of the alternator and engine.

1.2 Fuel System Inspection

✔ Ensure fuel lines are free from leaks.

✔ Verify that the fuel tank is properly vented and secured.

✔ Check the fuel filter and injectors for blockages.

1.3 Cooling System Inspection

✔ Check the radiator coolant levels.

✔ Inspect cooling fan belts for proper tension.

✔ Ensure the heat exchanger is clean and free from obstructions.

1.4 Battery & Electrical System Check

✔ Ensure the battery is fully charged and connections are secure.

✔ Check the Automatic Voltage Regulator (AVR) settings.

✔ Verify that the earthing system is properly installed.

2. Electrical Testing

Once the pre-commissioning checks are completed, electrical tests ensure the generator operates at the correct voltage, frequency, and load capacity.

2.1 Insulation Resistance Test

✔ Measures the insulation strength of generator windings.

✔ Conducted using a megger to check for insulation breakdown.

2.2 Voltage & Frequency Stability Test

✔ Ensures the generator maintains stable voltage (400V/230V) and frequency (50Hz or 60Hz) under different load conditions.

2.3 Phase Sequence Test

✔ Verifies that the generator’s phase sequence matches the connected load.

2.4 Grounding & Earthing Resistance Test

✔ Measures the neutral and body grounding resistance to ensure safe operation.

✔ Recommended earthing resistance: <1 ohm.

3. Mechanical Testing

Mechanical tests ensure the engine, alternator, and exhaust system function correctly.

3.1 Engine Performance Check

✔ Start the generator and check for abnormal vibrations or noises.

✔ Monitor oil pressure, coolant temperature, and exhaust temperature.

3.2 Fuel Consumption Test

✔ Records fuel efficiency at different load levels.

✔ Ensures fuel injection timing is properly adjusted.

4. Load Testing & Synchronization

Before putting the generator into full operation, it must undergo load testing to verify its ability to supply power without interruptions.

4.1 Load Bank Testing

✔ Simulates real-world conditions by gradually applying incremental loads.

✔ Ensures the generator can handle 100% rated load without voltage/frequency fluctuations.

4.2 Synchronization Check (For Multiple DG Sets)

✔ Verifies that multiple generators can operate in parallel.

✔ Ensures proper load sharing and phase synchronization.

5. Final Safety & Compliance Checks

Before handing over the generator for full operation, final safety checks must be performed.

✔ Ensure compliance with CPCB IV+ emission norms.

✔ Verify that the acoustic enclosure meets noise regulations.

✔ Check the Automatic Transfer Switch (ATS) functionality for seamless power switching.

6. Generator Commissioning Checklist

Physical & mechanical inspection completed

Fuel, lubrication, and cooling systems verified

Voltage, frequency, and insulation resistance tested

Load test conducted at full capacity

Earthing resistance checked

CPCB IV+ and IEC compliance verified

Wrapping Up

Proper generator commissioning ensures long-term efficiency, reliability, and compliance with industry standards. Following a structured commissioning procedure and checklist minimizes the risk of failures and ensures seamless power generation.

In the next blog, we will explore Generator Maintenance: Preventive, Predictive & Corrective Approaches. Stay tuned!



Kommentare


bottom of page