top of page
elearning@ensemble

Commissioning of Power Transformers: Procedures, Checklists, and Safety Measures


Commissioning of Power Transformer

Commissioning a power transformer is a critical process that ensures it operates safely and efficiently within the electrical system. It involves a series of inspections, tests, and settings that verify the transformer’s readiness for operation. In this blog, we’ll walk through the procedures, checklists, and safety measures for the commissioning of power transformers, highlighting the essential steps to guarantee a successful start-up.

1. Pre-Commissioning Inspections

Before energizing the transformer, it is crucial to conduct thorough visual and mechanical inspections to identify any potential issues.

1.1 Visual Inspection

  • Check for Damage: Inspect the transformer's external surfaces for signs of damage during transportation or installation, including dents, scratches, or oil leaks.

  • Oil Level: Ensure that the oil level in the conservator tank is within the specified range.

  • Bushings: Inspect the bushings for cracks or dirt accumulation, which could affect insulation.

  • Gaskets and Seals: Verify that all gaskets and seals are intact to prevent oil leakage.

1.2 Mechanical Inspection

  • Tightness: Check the tightness of all bolts, nuts, and clamps on the transformer's structure.

  • Valves and Radiators: Ensure that all valves (e.g., drain, fill, and sampling) are functional and that radiators are properly mounted.

2. Pre-Commissioning Electrical Tests

Testing the electrical components of the transformer is essential to verify its functionality and safety before it is energized.

2.1 Insulation Resistance Test

  • Objective: To ensure that the transformer's insulation is intact and free from moisture.

  • Procedure: Use a megger to apply a DC voltage across the windings and measure the resistance. The values should meet the manufacturer's specifications.

2.2 Winding Resistance Measurement

  • Objective: To detect issues like loose connections or winding faults.

  • Procedure: Pass a low DC current through the windings and measure the voltage drop to calculate the winding resistance.

2.3 Ratio Test

  • Objective: To confirm that the turn ratio between the primary and secondary windings matches the specified values.

  • Procedure: Apply a voltage to the primary winding and measure the output on the secondary to calculate the ratio.

2.4 Vector Group Test

  • Objective: To verify the phase displacement and polarity between the primary and secondary windings.

  • Procedure: Inject a voltage into one winding and measure the resulting voltages across the other windings to identify the vector group.

2.5 Dielectric Test

  • Separate Source AC Withstand Test: Applies high AC voltage to check insulation strength.

  • Induced Overvoltage Test: Ensures that the transformer can handle overvoltage conditions without insulation failure.

3. Relay Settings and Protection Schemes

Proper configuration of protection relays is crucial for safeguarding the transformer from faults and abnormalities.

3.1 Overcurrent Protection

  • Setting: Set the overcurrent relay to trip the circuit if the current exceeds the predefined limits, protecting against short circuits and overloads.

3.2 Inrush Current Protection

  • Setting: Adjust the inrush restraint settings to prevent unnecessary tripping when the transformer is initially energized, as inrush currents can be several times higher than the rated current.

3.3 Differential Protection

  • Setting: Calibrate the differential relay to detect any discrepancies between the current entering and leaving the transformer, indicating possible internal faults.

4. On-Load Tap Changer (OLTC) Inspection

The OLTC adjusts the transformer's output voltage based on load requirements. Proper inspection and setting are necessary to ensure smooth operation.

  • Check Oil Level: Ensure the OLTC compartment's oil level is correct.

  • Manual Operation Test: Perform manual operation of the tap changer to verify its mechanical functionality.

  • Motor Drive Test: Test the motor drive for automatic tap changing to ensure it responds correctly to voltage variations.

5. Final Checklist Before Energizing

  • Grounding: Verify that the transformer is properly grounded to prevent electrical hazards.

  • Neutral Earthing: Ensure that the neutral point is securely connected to the earth.

  • Cooling System: Check the cooling fans or pumps for proper operation in oil-filled transformers.

  • Oil Sampling: Collect and analyze oil samples to check for moisture content and dielectric strength.

  • Control Panel: Verify the functionality of the control panel, meters, and alarms.

6. Energizing the Transformer

With all inspections and tests completed, the transformer is now ready for energization. Follow these steps to safely power up the transformer:

  • Initial Energization: Gradually apply voltage to the primary side and monitor the current and voltage levels on both the primary and secondary sides.

  • Monitor Temperatures: Observe the winding and oil temperatures during the initial run to ensure they remain within safe limits.

  • Load Gradually: Gradually increase the load on the transformer while continuously monitoring all parameters.

7. Post-Commissioning Monitoring

After the transformer is successfully energized, continue to monitor its operation during the initial period to identify any irregularities.

  • Oil Temperature: Monitor the oil temperature using the oil temperature indicator (OTI).

  • Winding Temperature: Check the winding temperature to detect any overheating.

  • Load Currents: Verify that the load currents are balanced and within rated limits.

Wrapping Up

Commissioning a power transformer involves meticulous inspection, testing, and configuration to ensure it operates safely and reliably. By following a detailed procedure and adhering to safety standards, electrical engineers can significantly reduce the risk of faults and extend the transformer’s operational life.



Comments


bottom of page